{"id":2183,"date":"2024-01-14T13:06:32","date_gmt":"2024-01-14T13:06:32","guid":{"rendered":"https:\/\/murrayslatter.me\/?p=2183"},"modified":"2024-07-18T07:14:46","modified_gmt":"2024-07-17T21:14:46","slug":"coe-risk-1-fundamentals-of-risk-management","status":"publish","type":"post","link":"https:\/\/murrayslatter.me\/?p=2183","title":{"rendered":"CoE Risk #1: Fundamentals of Risk Management"},"content":{"rendered":"\n<h2 class=\"wp-block-heading\">What Great Looks Like: A Guide for Project and Program Managers<\/h2>\n\n\n\n<p>Risk management is a crucial function of any successful project or program. Effective risk management enables project and program managers to identify potential risks, assess their likelihood and impact, develop strategies to mitigate or respond to those risks, and ultimately minimize the negative impact of those risks on the project or program outcomes. Here I lay the series that introduces the Centre of Excellence (or CoE) of the Fundamentals of Risk Management<\/p>\n\n\n\n<h2 class=\"wp-block-heading\">Series<\/h2>\n\n\n\n<ol class=\"wp-block-list\" type=\"1\">\n<li>Understanding the Fundamentals of Risk Management: A Guide for Project and Program Managers (this post)<\/li>\n\n\n\n<li><a href=\"https:\/\/murrayslatter.me\/?p=2196\">Risk Identification and Assessment Techniques: Best Practices and Tools for Successful Risk Management<\/a><\/li>\n\n\n\n<li><a href=\"https:\/\/murrayslatter.me\/?p=2378\">Building a Strong Risk Culture: How to Foster Risk-Awareness in Your Program Team<\/a><\/li>\n\n\n\n<li><a href=\"https:\/\/murrayslatter.me\/?p=2379\">Developing a Robust Risk Management Plan: Key Components and Strategies for Success<\/a><\/li>\n\n\n\n<li><a href=\"https:\/\/murrayslatter.me\/?p=2380\">Risk Mitigation and Response Strategies: Lessons Learned from Successful Programs<\/a><\/li>\n\n\n\n<li><a href=\"https:\/\/murrayslatter.me\/?p=2381\">The Role of Risk Leadership in Program Success: How to Lead Your Team Through Uncertainty<\/a><\/li>\n\n\n\n<li><a href=\"https:\/\/murrayslatter.me\/?p=2382\">Integrating Risk Management into Program Governance: Best Practices and Examples from Leading Organizations<\/a><\/li>\n\n\n\n<li><a href=\"https:\/\/murrayslatter.me\/?p=2383\">Building a Resilient Program: How to Plan for and Manage Risks in an Evolving Landscape<\/a><\/li>\n\n\n\n<li><a href=\"https:\/\/murrayslatter.me\/?p=2384\">Risk Communication and Reporting: Strategies for Effective Stakeholder Engagement<\/a><\/li>\n\n\n\n<li><a href=\"https:\/\/murrayslatter.me\/?p=2385\">Managing Risks in Complex Programs: Lessons Learned from Large-Scale Projects<\/a><\/li>\n\n\n\n<li><a href=\"https:\/\/murrayslatter.me\/?p=2386\">The Role of Data and Analytics in Risk Management: Best Practices and Tools for Effective Risk Assessment<\/a><\/li>\n\n\n\n<li><a href=\"https:\/\/murrayslatter.me\/?p=2387\">Learning from Failure: How to Use Risk Management to Improve Program Performance<\/a><\/li>\n<\/ol>\n\n\n\n<p>In this series, we will explore the fundamentals of risk management, including key concepts and practices that project and program managers need to understand to effectively manage risks in their projects and programs.<\/p>\n\n\n\n<figure class=\"wp-block-embed is-type-rich is-provider-amazon wp-block-embed-amazon\"><div class=\"wp-block-embed__wrapper\">\n<iframe loading=\"lazy\" title=\"The Risk Management Handbook: A Practical Guide to Managing the Multiple Dimensions of Risk\" type=\"text\/html\" width=\"640\" height=\"550\" frameborder=\"0\" allowfullscreen style=\"max-width:100%\" src=\"https:\/\/read.amazon.com.au\/kp\/card?preview=inline&#038;linkCode=ll1&#038;ref_=k4w_oembed_wM5LlBavWSh9y2&#038;asin=B0BYF78LFY&#038;tag=bywineexecu09-22\"><\/iframe>\n<\/div><\/figure>\n\n\n\n<h2 class=\"wp-block-heading\">What is Risk (and Opportunity) Management?<\/h2>\n\n\n\n<p>Risk management is the process of identifying, assessing, and managing risks to achieve project or program objectives. Risk management involves identifying potential risks, assessing their likelihood and impact, developing strategies to mitigate or respond to those risks, and monitoring and controlling risks throughout the project or program lifecycle.<\/p>\n\n\n\n<p>Are you aware, Risk management is an iterative process that requires ongoing monitoring and reassessment of risks as new information becomes available? Effective risk management enables project and program managers to make informed decisions and take proactive measures to minimize the negative impact of risks on project or program outcomes.<\/p>\n\n\n\n<figure class=\"wp-block-embed is-type-rich is-provider-amazon wp-block-embed-amazon\"><div class=\"wp-block-embed__wrapper\">\n<iframe loading=\"lazy\" title=\"The Failure of Risk Management: Why It&#039;s Broken and How to Fix It\" type=\"text\/html\" width=\"640\" height=\"550\" frameborder=\"0\" allowfullscreen style=\"max-width:100%\" src=\"https:\/\/read.amazon.com.au\/kp\/card?preview=inline&#038;linkCode=ll1&#038;ref_=k4w_oembed_vYjuILwK5CdiSs&#038;asin=111952203X&#038;tag=bywineexecu09-22\"><\/iframe>\n<\/div><\/figure>\n\n\n\n<h2 class=\"wp-block-heading\">Key Concepts in Risk Management<\/h2>\n\n\n\n<p>There are several key concepts in risk management that project and program managers need to understand. These include:<\/p>\n\n\n\n<ol class=\"wp-block-list\" type=\"1\">\n<li><strong>Risk<\/strong>: A risk is an uncertain event or condition that, if it occurs, could have a positive or negative impact on project or program objectives.<\/li>\n\n\n\n<li><strong>Risk Probability: <\/strong>Risk probability is the likelihood that a risk will occur.<\/li>\n\n\n\n<li>Risk Impact: Risk impact is the magnitude of the effect that a risk could have on project or program objectives.<\/li>\n\n\n\n<li><strong>Risk Tolerance:<\/strong> Risk tolerance is the degree of risk that an organization is willing to accept.<\/li>\n\n\n\n<li><strong>Risk Mitigation: <\/strong>Risk mitigation involves developing strategies to reduce the likelihood or impact of a risk.<\/li>\n\n\n\n<li><strong>Risk Response: <\/strong>Risk response involves developing strategies to respond to a risk if it occurs.<\/li>\n<\/ol>\n\n\n\n<h2 class=\"wp-block-heading\">Fundamentals of Risk Management<\/h2>\n\n\n\n<p>Effective risk management involves several key practices that project and program managers need to understand. These practices for Fundamentals of Risk Management include:<\/p>\n\n\n\n<ol class=\"wp-block-list\" type=\"1\">\n<li><strong>Risk Identification: <\/strong>Risk identification involves identifying potential risks that could impact project or program objectives. This can be done through brainstorming, risk assessment workshops, or other techniques.<\/li>\n\n\n\n<li><strong>Risk Assessment: <\/strong>Risk assessment involves assessing the likelihood and impact of each identified risk. This can be done using quantitative or qualitative techniques, such as probability and impact matrices or expert judgment.<\/li>\n\n\n\n<li><strong>Risk Prioritization: <\/strong>Risk prioritization involves ranking identified risks based on their likelihood and impact. This enables project and program managers to focus their attention and resources on the most significant risks.<\/li>\n\n\n\n<li><strong>Risk Mitigation <\/strong>and <strong>Response Planning<\/strong>: Risk mitigation and response planning involves developing strategies to reduce the likelihood or impact of identified risks, or to respond to risks if they occur. This may involve developing contingency plans, implementing risk controls, or taking other measures.<\/li>\n\n\n\n<li><strong>Risk Monitoring and Control<\/strong>: Risk monitoring and control involves ongoing monitoring of identified risks, as well as implementing risk response strategies as necessary. This enables project and program managers to adapt to changing circumstances and proactively manage risks throughout the project or program lifecycle.<\/li>\n<\/ol>\n\n\n\n<figure class=\"wp-block-embed is-type-rich is-provider-amazon wp-block-embed-amazon\"><div class=\"wp-block-embed__wrapper\">\n<iframe loading=\"lazy\" title=\"Risk Management: Concepts and Guidance, Fifth Edition\" type=\"text\/html\" width=\"640\" height=\"550\" frameborder=\"0\" allowfullscreen style=\"max-width:100%\" src=\"https:\/\/read.amazon.com.au\/kp\/card?preview=inline&#038;linkCode=ll1&#038;ref_=k4w_oembed_u0KNPcJmQsipqk&#038;asin=1032340207&#038;tag=bywineexecu09-22\"><\/iframe>\n<\/div><\/figure>\n\n\n\n<h2 class=\"wp-block-heading\">Key Takeaways<\/h2>\n\n\n\n<p>Understanding the fundamentals of risk management is crucial for project and program managers. Effective risk management (ERM) enables project and program managers to identify potential risks, assess their likelihood and impact, develop strategies to mitigate or respond to those risks. Great ERM ultimately minimize the negative impact of those risks on the project or program outcomes.<\/p>\n\n\n\n<p>By understanding key concepts such as risk probability, impact, tolerance, mitigation, and response, as well as fundamental practices such as risk identification, assessment, prioritization, mitigation and response planning, and monitoring and control, project and program managers can be better equipped to manage risks effectively and achieve project and program success.<\/p>\n\n\n\n<h2 class=\"wp-block-heading\">The Best thinkers in ERM<\/h2>\n\n\n\n<p>Some of the best thinkers in the space of Effective risk management, along with examples of what separates great from good Understanding the Fundamentals of Risk Management:<\/p>\n\n\n\n<h3 class=\"wp-block-heading\">Douglas Hubbard: <\/h3>\n\n\n\n<p>Douglas Hubbard is the author of <a href=\"https:\/\/www.amazon.com.au\/Failure-Risk-Management-Broken-Second\/dp\/111952203X?crid=1UH23T49IJXHA&amp;keywords=%22The+Failure+of+Risk+Management%3A+Why+It%27s+Broken+and+How+to+Fix+It%2C%22&amp;qid=1704603007&amp;sprefix=the+failure+of+risk+management+why+it%27s+broken+and+how+to+fix+it+%2Caps%2C485&amp;sr=8-1&amp;linkCode=ll1&amp;tag=bywineexecu09-22&amp;linkId=7ecc8063a71c349fec1e055d33725f79&amp;language=en_AU&amp;ref_=as_li_ss_tl\">&#8220;The Failure of Risk Management: Why It&#8217;s Broken and How to Fix It,&#8221;<\/a> and is a leading expert in quantitative risk management. <\/p>\n\n\n\n<p>What separates great from good risk management? The ability to use quantitative techniques to assess risks and make informed decisions based on data.<\/p>\n\n\n\n<h3 class=\"wp-block-heading\">David Hillson: <\/h3>\n\n\n\n<p>David Hillson is the author of several books on risk management, including &#8220;Managing Risk in Projects&#8221; and <a href=\"https:\/\/www.amazon.com.au\/Risk-Management-Handbook-Practical-Dimensions-ebook\/dp\/B0BYF78LFY?crid=2E3S3YUUJ8LFQ&amp;keywords=hillson+%22The+Risk+Management+Handbook.%22&amp;qid=1704603058&amp;sprefix=hillson%22the+risk+management+handbook+%2Caps%2C219&amp;sr=8-1&amp;linkCode=ll1&amp;tag=bywineexecu09-22&amp;linkId=f7fe6bb3758135b01871d6963232426e&amp;language=en_AU&amp;ref_=as_li_ss_tl\">&#8220;The Risk Management Handbook.&#8221;<\/a> <\/p>\n\n\n\n<p>Hillson emphasizes a culture of risk management in the organization where all stakeholders are engaged in their role in managing risks.<\/p>\n\n\n\n<h3 class=\"wp-block-heading\">Carl Pritchard: <\/h3>\n\n\n\n<p>Carl Pritchard is a risk management consultant and author of <a href=\"https:\/\/www.amazon.com.au\/Risk-Management-Concepts-Guidance-Fifth\/dp\/1032340207?crid=2TQULQFQFKQFH&amp;keywords=%22Risk+Management%3A+Concepts+and+Guidance.%22+pritchard&amp;qid=1704603079&amp;sprefix=risk+management+concepts+and+guidance.%22+pritchar%2Caps%2C225&amp;sr=8-1&amp;linkCode=ll1&amp;tag=bywineexecu09-22&amp;linkId=60b9b9435b3be0e1ff1220caddc0a1a7&amp;language=en_AU&amp;ref_=as_li_ss_tl\">&#8220;Risk Management: Concepts and Guidance.&#8221;<\/a> Pritchard emphasizes the importance of risk communication, both within the organization and with external stakeholders, to ensure that everyone is aware of the risks and understands how they are being managed.<\/p>\n\n\n\n<h3 class=\"wp-block-heading\">Karen Tate: <\/h3>\n\n\n\n<p>Karen Tate is the author of &#8220;Adaptive Risk Management,&#8221; which emphasizes the importance of adapting risk management practices to meet the needs of the organization and the project or program. One of the things that separates great from good risk management is the ability to adapt to changing circumstances and use a flexible approach to managing risks.<\/p>\n\n\n\n<h2 class=\"wp-block-heading\">What Separates Great from Good?<\/h2>\n\n\n\n<p>Overall, what separates great from good risk management is the ability to use a holistic approach that considers the full range of risks and their potential impact, the ability to use data and quantitative techniques to inform decision-making, the ability to communicate effectively with stakeholders, and the ability to adapt to changing circumstances and use a flexible approach to managing risks. Great risk management is characterized by a culture of risk awareness and a commitment to managing risks proactively and strategically, rather than simply reacting to risks as they arise.<\/p>\n","protected":false},"excerpt":{"rendered":"<p>What Great Looks Like: A Guide for Project and Program Managers Risk management is a crucial function of any successful project or program. Effective risk management enables project and program managers to identify potential risks, assess their likelihood and impact, [&hellip;]<\/p>\n","protected":false},"author":2,"featured_media":2412,"comment_status":"open","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"content-type":"","_monsterinsights_skip_tracking":false,"_monsterinsights_sitenote_active":false,"_monsterinsights_sitenote_note":"","_monsterinsights_sitenote_category":0,"jetpack_post_was_ever_published":false,"_jetpack_newsletter_access":"","_jetpack_dont_email_post_to_subs":false,"_jetpack_newsletter_tier_id":0,"_jetpack_memberships_contains_paywalled_content":false,"_jetpack_memberships_contains_paid_content":false,"footnotes":""},"categories":[33,22],"tags":[87,51],"class_list":["post-2183","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-coe-risk-management","category-uniq","tag-coerisk","tag-series","clearfix"],"yoast_head":"<!-- This site is optimized with the Yoast SEO plugin v27.3 - https:\/\/yoast.com\/product\/yoast-seo-wordpress\/ -->\n<title>CoE Risk #1: Fundamentals of Risk Management - Murray Slatter<\/title>\n<meta name=\"description\" content=\"The Fundamentals of Risk Management are crucial for the success of any Company. How do you mitigate risks? Don&#039;t settle for Good, be GREAT!\" \/>\n<meta name=\"robots\" content=\"index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1\" \/>\n<link rel=\"canonical\" href=\"https:\/\/murrayslatter.me\/?p=2183\" \/>\n<meta property=\"og:locale\" content=\"en_US\" \/>\n<meta property=\"og:type\" content=\"article\" \/>\n<meta property=\"og:title\" content=\"CoE Risk #1: Fundamentals of Risk Management - Murray Slatter\" \/>\n<meta property=\"og:description\" content=\"The Fundamentals of Risk Management are crucial for the success of any Company. How do you mitigate risks? Don&#039;t settle for Good, be GREAT!\" \/>\n<meta property=\"og:url\" content=\"https:\/\/murrayslatter.me\/?p=2183\" \/>\n<meta property=\"og:site_name\" content=\"Murray Slatter\" \/>\n<meta property=\"article:published_time\" content=\"2024-01-14T13:06:32+00:00\" \/>\n<meta property=\"article:modified_time\" content=\"2024-07-17T21:14:46+00:00\" \/>\n<meta property=\"og:image\" content=\"https:\/\/murrayslatter.me\/wp-content\/uploads\/2023\/12\/Risk-CoE-Slide1.jpg\" \/>\n\t<meta property=\"og:image:width\" content=\"1280\" \/>\n\t<meta property=\"og:image:height\" content=\"720\" \/>\n\t<meta property=\"og:image:type\" content=\"image\/jpeg\" \/>\n<meta name=\"author\" content=\"Murray Slatter\" \/>\n<meta name=\"twitter:card\" content=\"summary_large_image\" \/>\n<meta name=\"twitter:label1\" content=\"Written by\" \/>\n\t<meta name=\"twitter:data1\" content=\"Murray Slatter\" \/>\n\t<meta name=\"twitter:label2\" content=\"Est. reading time\" \/>\n\t<meta name=\"twitter:data2\" content=\"6 minutes\" \/>\n<script type=\"application\/ld+json\" class=\"yoast-schema-graph\">{\"@context\":\"https:\\\/\\\/schema.org\",\"@graph\":[{\"@type\":\"Article\",\"@id\":\"https:\\\/\\\/murrayslatter.me\\\/?p=2183#article\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/murrayslatter.me\\\/?p=2183\"},\"author\":{\"name\":\"Murray Slatter\",\"@id\":\"https:\\\/\\\/murrayslatter.me\\\/#\\\/schema\\\/person\\\/9774d7f727e6b917f43267614574f6d5\"},\"headline\":\"CoE Risk #1: Fundamentals of Risk Management\",\"datePublished\":\"2024-01-14T13:06:32+00:00\",\"dateModified\":\"2024-07-17T21:14:46+00:00\",\"mainEntityOfPage\":{\"@id\":\"https:\\\/\\\/murrayslatter.me\\\/?p=2183\"},\"wordCount\":1353,\"commentCount\":0,\"image\":{\"@id\":\"https:\\\/\\\/murrayslatter.me\\\/?p=2183#primaryimage\"},\"thumbnailUrl\":\"https:\\\/\\\/i0.wp.com\\\/murrayslatter.me\\\/wp-content\\\/uploads\\\/2023\\\/12\\\/Risk-CoE-Slide1.jpg?fit=1280%2C720&ssl=1\",\"keywords\":[\"#CoERisk\",\"#Series\"],\"articleSection\":[\"CoE - Risk Management\",\"UniQ\"],\"inLanguage\":\"en\",\"potentialAction\":[{\"@type\":\"CommentAction\",\"name\":\"Comment\",\"target\":[\"https:\\\/\\\/murrayslatter.me\\\/?p=2183#respond\"]}]},{\"@type\":\"WebPage\",\"@id\":\"https:\\\/\\\/murrayslatter.me\\\/?p=2183\",\"url\":\"https:\\\/\\\/murrayslatter.me\\\/?p=2183\",\"name\":\"CoE Risk #1: Fundamentals of Risk Management - Murray Slatter\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/murrayslatter.me\\\/#website\"},\"primaryImageOfPage\":{\"@id\":\"https:\\\/\\\/murrayslatter.me\\\/?p=2183#primaryimage\"},\"image\":{\"@id\":\"https:\\\/\\\/murrayslatter.me\\\/?p=2183#primaryimage\"},\"thumbnailUrl\":\"https:\\\/\\\/i0.wp.com\\\/murrayslatter.me\\\/wp-content\\\/uploads\\\/2023\\\/12\\\/Risk-CoE-Slide1.jpg?fit=1280%2C720&ssl=1\",\"datePublished\":\"2024-01-14T13:06:32+00:00\",\"dateModified\":\"2024-07-17T21:14:46+00:00\",\"author\":{\"@id\":\"https:\\\/\\\/murrayslatter.me\\\/#\\\/schema\\\/person\\\/9774d7f727e6b917f43267614574f6d5\"},\"description\":\"The Fundamentals of Risk Management are crucial for the success of any Company. How do you mitigate risks? Don't settle for Good, be GREAT!\",\"breadcrumb\":{\"@id\":\"https:\\\/\\\/murrayslatter.me\\\/?p=2183#breadcrumb\"},\"inLanguage\":\"en\",\"potentialAction\":[{\"@type\":\"ReadAction\",\"target\":[\"https:\\\/\\\/murrayslatter.me\\\/?p=2183\"]}]},{\"@type\":\"ImageObject\",\"inLanguage\":\"en\",\"@id\":\"https:\\\/\\\/murrayslatter.me\\\/?p=2183#primaryimage\",\"url\":\"https:\\\/\\\/i0.wp.com\\\/murrayslatter.me\\\/wp-content\\\/uploads\\\/2023\\\/12\\\/Risk-CoE-Slide1.jpg?fit=1280%2C720&ssl=1\",\"contentUrl\":\"https:\\\/\\\/i0.wp.com\\\/murrayslatter.me\\\/wp-content\\\/uploads\\\/2023\\\/12\\\/Risk-CoE-Slide1.jpg?fit=1280%2C720&ssl=1\",\"width\":1280,\"height\":720,\"caption\":\"Risk management is a crucial function of any successful project or program. Effective risk management enables project and program managers to identify potential risks, assess their likelihood and impact, develop strategies to mitigate or respond to those risks, and ultimately minimize the negative impact of those risks on the project or program outcomes.\"},{\"@type\":\"BreadcrumbList\",\"@id\":\"https:\\\/\\\/murrayslatter.me\\\/?p=2183#breadcrumb\",\"itemListElement\":[{\"@type\":\"ListItem\",\"position\":1,\"name\":\"Home\",\"item\":\"https:\\\/\\\/murrayslatter.me\\\/\"},{\"@type\":\"ListItem\",\"position\":2,\"name\":\"CoE Risk #1: Fundamentals of Risk Management\"}]},{\"@type\":\"WebSite\",\"@id\":\"https:\\\/\\\/murrayslatter.me\\\/#website\",\"url\":\"https:\\\/\\\/murrayslatter.me\\\/\",\"name\":\"Murray Slatter\",\"description\":\"Empowering Good teams to be Great!\",\"potentialAction\":[{\"@type\":\"SearchAction\",\"target\":{\"@type\":\"EntryPoint\",\"urlTemplate\":\"https:\\\/\\\/murrayslatter.me\\\/?s={search_term_string}\"},\"query-input\":{\"@type\":\"PropertyValueSpecification\",\"valueRequired\":true,\"valueName\":\"search_term_string\"}}],\"inLanguage\":\"en\"},{\"@type\":\"Person\",\"@id\":\"https:\\\/\\\/murrayslatter.me\\\/#\\\/schema\\\/person\\\/9774d7f727e6b917f43267614574f6d5\",\"name\":\"Murray Slatter\",\"image\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en\",\"@id\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/8aa0f1751d211918ccc2037a8b3ce22431cec7bef7edf9c993cee70e20717c88?s=96&d=mm&r=g\",\"url\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/8aa0f1751d211918ccc2037a8b3ce22431cec7bef7edf9c993cee70e20717c88?s=96&d=mm&r=g\",\"contentUrl\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/8aa0f1751d211918ccc2037a8b3ce22431cec7bef7edf9c993cee70e20717c88?s=96&d=mm&r=g\",\"caption\":\"Murray Slatter\"},\"url\":\"https:\\\/\\\/murrayslatter.me\\\/?author=2\"}]}<\/script>\n<!-- \/ Yoast SEO plugin. -->","yoast_head_json":{"title":"CoE Risk #1: Fundamentals of Risk Management - Murray Slatter","description":"The Fundamentals of Risk Management are crucial for the success of any Company. How do you mitigate risks? Don't settle for Good, be GREAT!","robots":{"index":"index","follow":"follow","max-snippet":"max-snippet:-1","max-image-preview":"max-image-preview:large","max-video-preview":"max-video-preview:-1"},"canonical":"https:\/\/murrayslatter.me\/?p=2183","og_locale":"en_US","og_type":"article","og_title":"CoE Risk #1: Fundamentals of Risk Management - Murray Slatter","og_description":"The Fundamentals of Risk Management are crucial for the success of any Company. How do you mitigate risks? Don't settle for Good, be GREAT!","og_url":"https:\/\/murrayslatter.me\/?p=2183","og_site_name":"Murray Slatter","article_published_time":"2024-01-14T13:06:32+00:00","article_modified_time":"2024-07-17T21:14:46+00:00","og_image":[{"width":1280,"height":720,"url":"https:\/\/murrayslatter.me\/wp-content\/uploads\/2023\/12\/Risk-CoE-Slide1.jpg","type":"image\/jpeg"}],"author":"Murray Slatter","twitter_card":"summary_large_image","twitter_misc":{"Written by":"Murray Slatter","Est. reading time":"6 minutes"},"schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"Article","@id":"https:\/\/murrayslatter.me\/?p=2183#article","isPartOf":{"@id":"https:\/\/murrayslatter.me\/?p=2183"},"author":{"name":"Murray Slatter","@id":"https:\/\/murrayslatter.me\/#\/schema\/person\/9774d7f727e6b917f43267614574f6d5"},"headline":"CoE Risk #1: Fundamentals of Risk Management","datePublished":"2024-01-14T13:06:32+00:00","dateModified":"2024-07-17T21:14:46+00:00","mainEntityOfPage":{"@id":"https:\/\/murrayslatter.me\/?p=2183"},"wordCount":1353,"commentCount":0,"image":{"@id":"https:\/\/murrayslatter.me\/?p=2183#primaryimage"},"thumbnailUrl":"https:\/\/i0.wp.com\/murrayslatter.me\/wp-content\/uploads\/2023\/12\/Risk-CoE-Slide1.jpg?fit=1280%2C720&ssl=1","keywords":["#CoERisk","#Series"],"articleSection":["CoE - Risk Management","UniQ"],"inLanguage":"en","potentialAction":[{"@type":"CommentAction","name":"Comment","target":["https:\/\/murrayslatter.me\/?p=2183#respond"]}]},{"@type":"WebPage","@id":"https:\/\/murrayslatter.me\/?p=2183","url":"https:\/\/murrayslatter.me\/?p=2183","name":"CoE Risk #1: Fundamentals of Risk Management - Murray Slatter","isPartOf":{"@id":"https:\/\/murrayslatter.me\/#website"},"primaryImageOfPage":{"@id":"https:\/\/murrayslatter.me\/?p=2183#primaryimage"},"image":{"@id":"https:\/\/murrayslatter.me\/?p=2183#primaryimage"},"thumbnailUrl":"https:\/\/i0.wp.com\/murrayslatter.me\/wp-content\/uploads\/2023\/12\/Risk-CoE-Slide1.jpg?fit=1280%2C720&ssl=1","datePublished":"2024-01-14T13:06:32+00:00","dateModified":"2024-07-17T21:14:46+00:00","author":{"@id":"https:\/\/murrayslatter.me\/#\/schema\/person\/9774d7f727e6b917f43267614574f6d5"},"description":"The Fundamentals of Risk Management are crucial for the success of any Company. How do you mitigate risks? Don't settle for Good, be GREAT!","breadcrumb":{"@id":"https:\/\/murrayslatter.me\/?p=2183#breadcrumb"},"inLanguage":"en","potentialAction":[{"@type":"ReadAction","target":["https:\/\/murrayslatter.me\/?p=2183"]}]},{"@type":"ImageObject","inLanguage":"en","@id":"https:\/\/murrayslatter.me\/?p=2183#primaryimage","url":"https:\/\/i0.wp.com\/murrayslatter.me\/wp-content\/uploads\/2023\/12\/Risk-CoE-Slide1.jpg?fit=1280%2C720&ssl=1","contentUrl":"https:\/\/i0.wp.com\/murrayslatter.me\/wp-content\/uploads\/2023\/12\/Risk-CoE-Slide1.jpg?fit=1280%2C720&ssl=1","width":1280,"height":720,"caption":"Risk management is a crucial function of any successful project or program. Effective risk management enables project and program managers to identify potential risks, assess their likelihood and impact, develop strategies to mitigate or respond to those risks, and ultimately minimize the negative impact of those risks on the project or program outcomes."},{"@type":"BreadcrumbList","@id":"https:\/\/murrayslatter.me\/?p=2183#breadcrumb","itemListElement":[{"@type":"ListItem","position":1,"name":"Home","item":"https:\/\/murrayslatter.me\/"},{"@type":"ListItem","position":2,"name":"CoE Risk #1: Fundamentals of Risk Management"}]},{"@type":"WebSite","@id":"https:\/\/murrayslatter.me\/#website","url":"https:\/\/murrayslatter.me\/","name":"Murray Slatter","description":"Empowering Good teams to be Great!","potentialAction":[{"@type":"SearchAction","target":{"@type":"EntryPoint","urlTemplate":"https:\/\/murrayslatter.me\/?s={search_term_string}"},"query-input":{"@type":"PropertyValueSpecification","valueRequired":true,"valueName":"search_term_string"}}],"inLanguage":"en"},{"@type":"Person","@id":"https:\/\/murrayslatter.me\/#\/schema\/person\/9774d7f727e6b917f43267614574f6d5","name":"Murray Slatter","image":{"@type":"ImageObject","inLanguage":"en","@id":"https:\/\/secure.gravatar.com\/avatar\/8aa0f1751d211918ccc2037a8b3ce22431cec7bef7edf9c993cee70e20717c88?s=96&d=mm&r=g","url":"https:\/\/secure.gravatar.com\/avatar\/8aa0f1751d211918ccc2037a8b3ce22431cec7bef7edf9c993cee70e20717c88?s=96&d=mm&r=g","contentUrl":"https:\/\/secure.gravatar.com\/avatar\/8aa0f1751d211918ccc2037a8b3ce22431cec7bef7edf9c993cee70e20717c88?s=96&d=mm&r=g","caption":"Murray Slatter"},"url":"https:\/\/murrayslatter.me\/?author=2"}]}},"jetpack_featured_media_url":"https:\/\/i0.wp.com\/murrayslatter.me\/wp-content\/uploads\/2023\/12\/Risk-CoE-Slide1.jpg?fit=1280%2C720&ssl=1","jetpack-related-posts":[{"id":2382,"url":"https:\/\/murrayslatter.me\/?p=2382","url_meta":{"origin":2183,"position":0},"title":"CoE Risk #7: Risk and Program Governance","author":"Murray Slatter","date":"January 14, 2024","format":false,"excerpt":"Best Practices and Examples from Leading Organizations The world of project and program management is fraught with uncertainties that can jeopardize even the most well-planned projects. Understanding the fundamentals of Risk and Program Governance is not merely about being cautious but about being smart and strategic in anticipating, analyzing, and\u2026","rel":"","context":"In &quot;CoE - Risk Management&quot;","block_context":{"text":"CoE - Risk Management","link":"https:\/\/murrayslatter.me\/?cat=33"},"img":{"alt_text":"","src":"https:\/\/i0.wp.com\/murrayslatter.me\/wp-content\/uploads\/2023\/12\/Risk-CoE-Slide8.jpg?fit=1200%2C675&ssl=1&resize=350%2C200","width":350,"height":200,"srcset":"https:\/\/i0.wp.com\/murrayslatter.me\/wp-content\/uploads\/2023\/12\/Risk-CoE-Slide8.jpg?fit=1200%2C675&ssl=1&resize=350%2C200 1x, https:\/\/i0.wp.com\/murrayslatter.me\/wp-content\/uploads\/2023\/12\/Risk-CoE-Slide8.jpg?fit=1200%2C675&ssl=1&resize=525%2C300 1.5x, https:\/\/i0.wp.com\/murrayslatter.me\/wp-content\/uploads\/2023\/12\/Risk-CoE-Slide8.jpg?fit=1200%2C675&ssl=1&resize=700%2C400 2x, https:\/\/i0.wp.com\/murrayslatter.me\/wp-content\/uploads\/2023\/12\/Risk-CoE-Slide8.jpg?fit=1200%2C675&ssl=1&resize=1050%2C600 3x"},"classes":[]},{"id":2196,"url":"https:\/\/murrayslatter.me\/?p=2196","url_meta":{"origin":2183,"position":1},"title":"CoE Risk #2: Risk Identification and Assessment Techniques","author":"Murray Slatter","date":"January 14, 2024","format":false,"excerpt":"What Great Looks Like: Best Practices and Tools for Successful Risk Management Risk management is a critical aspect of program management. In order to ensure the success of a program, project managers must be able to identify and assess potential risks, and implement effective risk management strategies to mitigate those\u2026","rel":"","context":"In &quot;CoE - Risk Management&quot;","block_context":{"text":"CoE - Risk Management","link":"https:\/\/murrayslatter.me\/?cat=33"},"img":{"alt_text":"","src":"https:\/\/i0.wp.com\/murrayslatter.me\/wp-content\/uploads\/2023\/12\/Risk-CoE-Slide3.jpg?fit=1200%2C675&ssl=1&resize=350%2C200","width":350,"height":200,"srcset":"https:\/\/i0.wp.com\/murrayslatter.me\/wp-content\/uploads\/2023\/12\/Risk-CoE-Slide3.jpg?fit=1200%2C675&ssl=1&resize=350%2C200 1x, https:\/\/i0.wp.com\/murrayslatter.me\/wp-content\/uploads\/2023\/12\/Risk-CoE-Slide3.jpg?fit=1200%2C675&ssl=1&resize=525%2C300 1.5x, https:\/\/i0.wp.com\/murrayslatter.me\/wp-content\/uploads\/2023\/12\/Risk-CoE-Slide3.jpg?fit=1200%2C675&ssl=1&resize=700%2C400 2x, https:\/\/i0.wp.com\/murrayslatter.me\/wp-content\/uploads\/2023\/12\/Risk-CoE-Slide3.jpg?fit=1200%2C675&ssl=1&resize=1050%2C600 3x"},"classes":[]},{"id":2147,"url":"https:\/\/murrayslatter.me\/?p=2147","url_meta":{"origin":2183,"position":2},"title":"CoE #5 : COST &#8211; The Role of Risk Management in Program Cost Control","author":"Murray Slatter","date":"November 13, 2023","format":false,"excerpt":"Program cost control is an essential aspect of project management, and risk management plays a vital role in ensuring that program costs are effectively controlled. The process of identifying and assessing risks, and developing strategies to mitigate those risks, can help to minimize cost overruns and keep programs on track.\u2026","rel":"","context":"In &quot;CoE - Program Management&quot;","block_context":{"text":"CoE - Program Management","link":"https:\/\/murrayslatter.me\/?cat=32"},"img":{"alt_text":"","src":"https:\/\/i0.wp.com\/murrayslatter.me\/wp-content\/uploads\/2023\/11\/Cost-Excellence-in-Program-Management-Slide6.jpg?fit=1200%2C675&ssl=1&resize=350%2C200","width":350,"height":200,"srcset":"https:\/\/i0.wp.com\/murrayslatter.me\/wp-content\/uploads\/2023\/11\/Cost-Excellence-in-Program-Management-Slide6.jpg?fit=1200%2C675&ssl=1&resize=350%2C200 1x, https:\/\/i0.wp.com\/murrayslatter.me\/wp-content\/uploads\/2023\/11\/Cost-Excellence-in-Program-Management-Slide6.jpg?fit=1200%2C675&ssl=1&resize=525%2C300 1.5x, https:\/\/i0.wp.com\/murrayslatter.me\/wp-content\/uploads\/2023\/11\/Cost-Excellence-in-Program-Management-Slide6.jpg?fit=1200%2C675&ssl=1&resize=700%2C400 2x, https:\/\/i0.wp.com\/murrayslatter.me\/wp-content\/uploads\/2023\/11\/Cost-Excellence-in-Program-Management-Slide6.jpg?fit=1200%2C675&ssl=1&resize=1050%2C600 3x"},"classes":[]},{"id":2226,"url":"https:\/\/murrayslatter.me\/?p=2226","url_meta":{"origin":2183,"position":3},"title":"PMF #3 of 12: Managing Risks in Capital Programs","author":"Murray Slatter","date":"January 20, 2024","format":false,"excerpt":"Great Risk management is foundation in capital program management. Risks can cause major disruptions leading project and program failure.","rel":"","context":"In &quot;CoE - Program Management Fundimentals&quot;","block_context":{"text":"CoE - Program Management Fundimentals","link":"https:\/\/murrayslatter.me\/?cat=34"},"img":{"alt_text":"Effective risk management is an essential part of successful capital program management.","src":"https:\/\/i0.wp.com\/murrayslatter.me\/wp-content\/uploads\/2024\/01\/QF-002-1-401-Linkedin-Brand-Slide-Program-ManagementSlide4.jpg?fit=1200%2C675&ssl=1&resize=350%2C200","width":350,"height":200,"srcset":"https:\/\/i0.wp.com\/murrayslatter.me\/wp-content\/uploads\/2024\/01\/QF-002-1-401-Linkedin-Brand-Slide-Program-ManagementSlide4.jpg?fit=1200%2C675&ssl=1&resize=350%2C200 1x, https:\/\/i0.wp.com\/murrayslatter.me\/wp-content\/uploads\/2024\/01\/QF-002-1-401-Linkedin-Brand-Slide-Program-ManagementSlide4.jpg?fit=1200%2C675&ssl=1&resize=525%2C300 1.5x, https:\/\/i0.wp.com\/murrayslatter.me\/wp-content\/uploads\/2024\/01\/QF-002-1-401-Linkedin-Brand-Slide-Program-ManagementSlide4.jpg?fit=1200%2C675&ssl=1&resize=700%2C400 2x, https:\/\/i0.wp.com\/murrayslatter.me\/wp-content\/uploads\/2024\/01\/QF-002-1-401-Linkedin-Brand-Slide-Program-ManagementSlide4.jpg?fit=1200%2C675&ssl=1&resize=1050%2C600 3x"},"classes":[]},{"id":2142,"url":"https:\/\/murrayslatter.me\/?p=2142","url_meta":{"origin":2183,"position":4},"title":"CoE &#8211; COST &#8211; Excellence in Program Management","author":"Murray Slatter","date":"November 5, 2023","format":false,"excerpt":"What Great Looks Like - Cost Management in Program Management Over the next few weeks, I shall share a series of posts entitled \"What Great looks like - Cost Management in Program Management\" https:\/\/www.amazon.com.au\/Guide-Project-Management-Knowledge-Pmbok\/dp\/1628256648?crid=K1ZHYXIFCVSP&keywords=PMBOK&qid=1699072363&sprefix=pmbok%2Caps%2C317&sr=8-3&linkCode=ll1&tag=bywineexecu09-22&linkId=a3ef0c3577db29c34ace6248490779d7&language=en_AU&ref_=as_li_ss_tl I have developed these thoughts and am sharing them here to contribute to the growing body\u2026","rel":"","context":"In &quot;CoE - Program Management&quot;","block_context":{"text":"CoE - Program Management","link":"https:\/\/murrayslatter.me\/?cat=32"},"img":{"alt_text":"Best Practice - Cost Excellence in Program Management","src":"https:\/\/i0.wp.com\/murrayslatter.me\/wp-content\/uploads\/2023\/11\/Cost-Excellence-in-Program-Management-Slide1.jpg?fit=1200%2C675&ssl=1&resize=350%2C200","width":350,"height":200,"srcset":"https:\/\/i0.wp.com\/murrayslatter.me\/wp-content\/uploads\/2023\/11\/Cost-Excellence-in-Program-Management-Slide1.jpg?fit=1200%2C675&ssl=1&resize=350%2C200 1x, https:\/\/i0.wp.com\/murrayslatter.me\/wp-content\/uploads\/2023\/11\/Cost-Excellence-in-Program-Management-Slide1.jpg?fit=1200%2C675&ssl=1&resize=525%2C300 1.5x, https:\/\/i0.wp.com\/murrayslatter.me\/wp-content\/uploads\/2023\/11\/Cost-Excellence-in-Program-Management-Slide1.jpg?fit=1200%2C675&ssl=1&resize=700%2C400 2x, https:\/\/i0.wp.com\/murrayslatter.me\/wp-content\/uploads\/2023\/11\/Cost-Excellence-in-Program-Management-Slide1.jpg?fit=1200%2C675&ssl=1&resize=1050%2C600 3x"},"classes":[]},{"id":2380,"url":"https:\/\/murrayslatter.me\/?p=2380","url_meta":{"origin":2183,"position":5},"title":"CoE Risk #5: Risk Mitigation and Response Strategies","author":"Murray Slatter","date":"January 14, 2024","format":false,"excerpt":"Lessons Learned from Successful Programs When it comes to risk mitigation and response strategies, the difference between a good program and a great one often comes down to the depth of understanding and the application of learned lessons. This blog aims to stretch the professional acumen of project managers by\u2026","rel":"","context":"In &quot;CoE - Risk Management&quot;","block_context":{"text":"CoE - Risk Management","link":"https:\/\/murrayslatter.me\/?cat=33"},"img":{"alt_text":"","src":"https:\/\/i0.wp.com\/murrayslatter.me\/wp-content\/uploads\/2023\/12\/Risk-CoE-Slide6.jpg?fit=1200%2C675&ssl=1&resize=350%2C200","width":350,"height":200,"srcset":"https:\/\/i0.wp.com\/murrayslatter.me\/wp-content\/uploads\/2023\/12\/Risk-CoE-Slide6.jpg?fit=1200%2C675&ssl=1&resize=350%2C200 1x, https:\/\/i0.wp.com\/murrayslatter.me\/wp-content\/uploads\/2023\/12\/Risk-CoE-Slide6.jpg?fit=1200%2C675&ssl=1&resize=525%2C300 1.5x, https:\/\/i0.wp.com\/murrayslatter.me\/wp-content\/uploads\/2023\/12\/Risk-CoE-Slide6.jpg?fit=1200%2C675&ssl=1&resize=700%2C400 2x, https:\/\/i0.wp.com\/murrayslatter.me\/wp-content\/uploads\/2023\/12\/Risk-CoE-Slide6.jpg?fit=1200%2C675&ssl=1&resize=1050%2C600 3x"},"classes":[]}],"jetpack_sharing_enabled":true,"_links":{"self":[{"href":"https:\/\/murrayslatter.me\/index.php?rest_route=\/wp\/v2\/posts\/2183","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/murrayslatter.me\/index.php?rest_route=\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/murrayslatter.me\/index.php?rest_route=\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/murrayslatter.me\/index.php?rest_route=\/wp\/v2\/users\/2"}],"replies":[{"embeddable":true,"href":"https:\/\/murrayslatter.me\/index.php?rest_route=%2Fwp%2Fv2%2Fcomments&post=2183"}],"version-history":[{"count":5,"href":"https:\/\/murrayslatter.me\/index.php?rest_route=\/wp\/v2\/posts\/2183\/revisions"}],"predecessor-version":[{"id":2605,"href":"https:\/\/murrayslatter.me\/index.php?rest_route=\/wp\/v2\/posts\/2183\/revisions\/2605"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/murrayslatter.me\/index.php?rest_route=\/wp\/v2\/media\/2412"}],"wp:attachment":[{"href":"https:\/\/murrayslatter.me\/index.php?rest_route=%2Fwp%2Fv2%2Fmedia&parent=2183"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/murrayslatter.me\/index.php?rest_route=%2Fwp%2Fv2%2Fcategories&post=2183"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/murrayslatter.me\/index.php?rest_route=%2Fwp%2Fv2%2Ftags&post=2183"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}